SAP PS Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PS. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : C

Explanation

You can also categorize projects according to the list of activities and project structure or on the basis of individual activities:

  • Using Work break down structure WBS
  • Using individual activities as per work packages

Q 2 - In Project system, it is also possible to assign any object currency to which of the following objects in the system?

A - WBS element

B - Project definition

C - Network header

D - Network activity

E - All of the above

Answer : E

Explanation

Object currency:

In Project system, it is also possible to assign any object currency to different objects in the system.

  • WBS element
  • Project definition
  • Network header
  • Network activity

Q 3 - In SAP Project system, you define the activities and people in the project in form of?

A - Company code

B - Work Breakdown Structure

C - Storage location

D - Project Charter

Answer : B

Explanation

Work Breakdown structure:

This is first step in project planning to define work breakdown structure to divide the activities into tasks. The type of tasks and activities to be defined vary as per project complexity and type of project- customer based or internal project.

In SAP Project system, you define the activities and people in the project in form of Work breakdown structure WBS.

Q 4 - Which of the following is used to define the work order that has a structure in common with production, maintenance and inspection orders?

A - Network

B - Production Order

C - Settlement Profile

D - None of the above

Answer : A

Q 5 - In Project System, all currency related data is managed in which of the following currency types?

A - Controlling Area Currency

B - Object Currency

C - Transaction Currency

D - All of the above

Answer : D

Q 6 - In SAP Project System, if you require more than 9999 components in one network then you may use subnetworks?

A - True

B - False

Answer : A

Q 7 - Which of the following Transaction Code is used to create Budget profile?

A - OPS9

B - OPSK

C - OPS3

D - OK02

Answer : A

Answer : C

Q 9 - Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets?

A - Read Authorization

B - Change Authorization

C - Both of the above

Answer : B

Explanation

Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets change authorization in this scenario.

Q 10 - Budget is defined as approved cost for a project and it is same as the cost plan?

A - True

B - False

Answer : B

Explanation

Budget is defined as approved cost for a project and it is different from the cost plan. Budget is approved cost from management for expected development of order cost for a given time period.