- SAP PS - Home
- SAP PS - Overview
- Integration with ERP Modules
- Organization Structure Elements
- SAP PS - Currencies
- SAP PS - What is a Project?
- SAP PS - Defining Special Characters
- SAP PS - Status Profile
- SAP PS - Selection Profile
- SAP PS - Project Profile
- SAP PS - Settlement Profile
- SAP PS - Network Profile
- SAP PS - Network Type
- Person Responsible for Work Center
- Maintain Activity Control Key
- SAP PS - Access Control List
- SAP PS - Cost Component
- SAP PS - Execution Service Profile
- SAP PS - Budget Management
- Number Ranges for Budgeting
- SAP PS - Revenues and Earnings
- SAP PS - Dates
- WBS Scheduling Parameters
- SAP PS - Material
- SAP PS - Versions
- SAP PS - Project Information System
- SAP PS - Consultant Responsibilities
SAP PS Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP PS. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Q 1 - In SAP Project system, a project can be categorized as?
A - Using Work break down structure WBS
Answer : C
Explanation
You can also categorize projects according to the list of activities and project structure or on the basis of individual activities:
- Using Work break down structure WBS
- Using individual activities as per work packages
Q 2 - In Project system, it is also possible to assign any object currency to which of the following objects in the system?
Answer : E
Explanation
Object currency:
In Project system, it is also possible to assign any object currency to different objects in the system.
- WBS element
- Project definition
- Network header
- Network activity
Q 3 - In SAP Project system, you define the activities and people in the project in form of?
Answer : B
Explanation
Work Breakdown structure:
This is first step in project planning to define work breakdown structure to divide the activities into tasks. The type of tasks and activities to be defined vary as per project complexity and type of project- customer based or internal project.
In SAP Project system, you define the activities and people in the project in form of Work breakdown structure WBS.
Q 4 - Which of the following is used to define the work order that has a structure in common with production, maintenance and inspection orders?
Answer : A
Q 5 - In Project System, all currency related data is managed in which of the following currency types?
Answer : D
Q 6 - In SAP Project System, if you require more than 9999 components in one network then you may use subnetworks?
Answer : A
Q 7 - Which of the following Transaction Code is used to create Budget profile?
Answer : A
Q 8 - In SAP PS system, a control key is identified by?
B - Three digit alphanumeric ID
Answer : C
Q 9 - Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets?
Answer : B
Explanation
Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets change authorization in this scenario.
Q 10 - Budget is defined as approved cost for a project and it is same as the cost plan?
Answer : B
Explanation
Budget is defined as approved cost for a project and it is different from the cost plan. Budget is approved cost from management for expected development of order cost for a given time period.