- SAP QM Tutorial
- SAP QM - Home
- SAP QM - Overview
- SAP QM - Components
- SAP QM - Integration
- SAP QM - Master Data
- SAP QM - Inspection Methods
- SAP QM - Sampling
- SAP QM - Inspection Plan
- SAP QM - Quality Info Records
- SAP QM - Lot Inspection
- SAP QM - Result Recording
- SAP QM - Usage Decision
- SAP QM - Listing Inspection Lot
- SAP QM - In-Process Inspection
- SAP QM - Final Inspection
- SAP QM - Defects Recording
- SAP QM - Quality Notification
- SAP QM - Benefits
- SAP QM - Tables
- Consultant Responsibilities
- SAP QM Useful Resources
- SAP QM - Questions Answers
- SAP QM - Quick Guide
- SAP QM - Useful Resources
- SAP QM - Discussion
SAP QM Mock Test
This section presents you various set of Mock Tests related to SAP QM. You can download these sample mock tests at your local machine and solve offline at your convenience. Every mock test is supplied with a mock test key to let you verify the final score and grade yourself.
SAP QM Mock Test IV
Q 1 - To release and complete quality notification in SAP system, which of the following T-code is used?
Answer : B
Explanation
To release and complete quality notification in SAP system, use T-Code: QM02
Q 2 - Arrange the following steps in correct Order −
- Sampling
- Result recording
- Usage decision
- Posting the stock
Answer : A
Explanation
Final inspection process consists of the following steps −
- Creation and Confirmation of Production order
- Listing Inspection lot
- Attaching and releasing inspection lot
- Sampling
- Result recording
- Usage decision
- Posting the stock
Q 3 - For each good receipt, SAP system creates a one inspection lot which contains details- vendor, date or purchase, etc.?
Answer : A
Q 4 - If you want to display Quality Management standard forms, which of the following can be used?
Answer : A
Q 5 - Which of the following control chart can be used for specifying tolerance and control the share of scrap?
Answer : C
Q 6 - Which of the following document types are considered as Procurement document in procurement cycle?
Answer : B
Q 8 - As part of Quality Management process, which of the following parameter can be set for Material master?
Answer : D
Q 9 - In QM process, when a task list is created for an inspection lot which of the following is available for inspection?
Answer : C
Q 10 - In a Quality Info Record, it is possible to that inspection is required when it is procured from vendor A and is not required if you procure from Vendor B?
Answer : A
Q 11 - In a Sampling scheme, variable inspections include −
Answer : C
Explanation
The sample size, acceptance number, and rejection number for attributive inspections and sample size and K-factor for variable inspections.
Q 12 - Which of the following can be used to adjust the probability of acceptance and the inspection effort, based on different quality situations?
Answer : A
Explanation
In SAP Quality Management process, you can vary inspection severity that allows to adjust the probability of acceptance and the inspection effort, based on different quality situations. The inspection severity is closely connected to the inspection scope. If all other conditions remain the same, different inspection severities lead to different inspection scopes or acceptance conditions.
Q 13 - Which of the following module is integrated with QM to manage the costs for defect control and non-confirmative costs in production process?
Answer : D
Explanation
You can integrate SAP QM with controlling process to manage the costs for defect control and nonconfirmative costs in production process.
Answer Sheet
Question Number | Answer Key |
---|---|
1 | B |
2 | A |
3 | A |
4 | A |
5 | C |
6 | B |
7 | B |
8 | D |
9 | C |
10 | A |
11 | C |
12 | A |
13 | D |