- SAP CCA Tutorial
- SAP CCA - Home
- SAP CCA - Overview
- SAP CCA - Activity Types
- SAP CCA - Master Data
- SAP CCA - Cost Center Groups
- SAP CCA - Creating a Cost Center
- SAP CCA - Cost Center Posting
- SAP CCA - Linking Order Reason
- SAP CCA - Internal Order
- SAP CCA - Settlement of IO
- SAP CCA - Profit Center
- SAP CCA - Postings to Profit Center
- Profit Center Standard Hierarchy
- Assignment of Cost to Profit Centers
- Assigning Materials to Profit Center
- SAP CCA - Compare CO, PC, IO
- SAP CCA - Planning
- SAP CCA - Period-End Closing
- SAP CCA - Accrual Calculation
- SAP CCA - Schedule Manager
- SAP CCA - Variance Calculation
- SAP CCA - Year-End Closing
- SAP CCA - Product Costing
- SAP CCA - Profitability Analysis
- SAP CCA - Information System
- SAP CCA - Standard Reports
- SAP CCA - Important Tables
- SAP CCA - Job Responsibilities
- SAP CCA - Useful Resources
- SAP CCA - Questions Answers
- SAP CCA - Quick Guide
- SAP CCA - Useful Resources
- SAP CCA - Discussion
SAP CCA Mock Test
This section presents you various set of Mock Tests related to SAP CCA. You can download these sample mock tests at your local machine and solve offline at your convenience. Every mock test is supplied with a mock test key to let you verify the final score and grade yourself.
SAP CCA Mock Test II
Q 1 - While creating a Cost element group structure, you can create which of the following elements in Cost element group structure?
Answer : E
Q 2 - Which of the following can be used to copy actuals to a target planning version?
Answer : A
Q 3 - Which of the following determines where costs are incurred in the organization?
Answer : A
Q 4 - Which of the following can be used to monitor the costs of a time-restricted job or the costs for the production of activities or can also be used for the long-term monitoring of costs?
Answer : B
Explanation
SAP CO internal order monitor the parts of the costs and in few cases, the revenues of the organization.
You can create an internal order to monitor the costs of a time-restricted job or the costs for the production of activities. Internal orders can also be used for the long-term monitoring of costs.
Investment cost related to fixed assets are monitored using Investment orders.
Q 5 - If you are able to create a primary cost element in SAP CO system. What would you check first?
A - A Valid Cost Element Category exists
Answer : B
Q 6 - Which of the following currency type is used for cost accounting and is based on assignment control indicator and currency type?
Answer : A
Explanation
Controlling area currency
The system uses this currency for cost accounting. This currency is set up when you create the controlling area. It is based on the assignment control indicator and the currency type.
Q 7 - The transaction currency can differ from the controlling area currency and the object currency?
Answer : A
Q 8 - Which of the following provides a transaction-based and cross-functional approach for activity output in which several cost centers are involved?
Answer : C
Q 9 - In SAP system, you consider Controlling (CO) and Financial Accounting (FI) as two independent components and data flow occurs between two components?
Answer : A
Q 10 - Costs and revenues incurred for activities for external partners or for internal activities that do not form part of the core business for your organization are monitored using?
Answer : D
Explanation
Investment cost related to fixed assets are monitored using Investment orders.
Period-related accrual calculation between expenses in FI and the costing-based costs debited in Cost Accounting are monitored using Accrual orders.
Costs and revenues incurred for activities for external partners or for internal activities that do not form part of the core business for your organization are monitored using order with revenues.
Q 11 - An internal Order is used as an interim collector of costs and is used for planning, monitoring, and when job has been completed, you settle the costs to one or more receivers like cost centers, fixed assets, etc.?
Answer : A
Q 12 - How to perform settlement of IO to Cost Centers?
Answer : A
Answer Sheet
Question Number | Answer Key |
---|---|
1 | E |
2 | A |
3 | A |
4 | B |
5 | B |
6 | A |
7 | A |
8 | C |
9 | A |
10 | D |
11 | A |
12 | A |