Following quiz provides Multiple Choice Questions (MCQs) related to SAP QM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 2 - You can assign an inspection method to master inspection charactertics or directly to an inspection charactertics in an inspection plan?

A - True

B - False

Answer : A

Explanation

You can use inspection method to perform the inspection. An inspection method can be assigned to master inspection charactertics or directly to an inspection charactertics in an inspection plan.

An Inspection method can be created in one plant same method can be used in other plant.

Q 3 - A sampling plan defines the sample size specification for the inspection lot to determine if a sample is accepted or not accepted?

A - True

B - False

Answer : A

Q 4 - Which of the following comes under scope of Quality Control in Quality Management Plan?

A - Controlling

B - Inspection Plan

C - Raw Material

D - Final Product

Answer : D

Explanation

The quality notification process includes recording problem that is either identified by a customer for a product manufactured in an organization, or in a company against the product of a supplier/vendor.

Q 5 - When you chose a fixed sample and an attributive inspection for the valuation mode, you need to select following for sample data?

A - Enter the sample size and the acceptance number

B - Enter the sample size and the k-factor

C - Enter the sample size

D - Enter the inspection frequency

Answer : A

Explanation

Q 7 - What is the standard SAP QM notification type to record a complaint against vendor and take action for the incoming material?

A - Q1

B - Q2

C - Q3

D - Not Defined

Answer : B

Explanation

You can use standard SAP QM notification type Q2 to record a complaint against vendor and take action for the incoming material.

Q 8 - Which of the following Transaction code is used for scheduling UD for Production lot?

A - QA39

B - QA40

C - QA41

D - QA42

Answer : C

Q 9 - Which of the following control chart can be used for specifying tolerance and control the share of scrap?

A - Mean Value Chart

B - Statistical Chart

C - Acceptance Chart

D - All of the above

Answer : C

Q 10 - Which of the following module is integrated with QM to manage the costs for defect control and non-confirmative costs in production process?

A - SAP Material Management

B - SAP Production Planning

C - SAP Sales and Distribution

D - SAP Controlling

Answer : D

Explanation

You can integrate SAP QM with controlling process to manage the costs for defect control and nonconfirmative costs in production process.