SAP MM Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP MM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - Which of the following module is a part of Logistics area and helps to manage the procurement activity of an organization from procurement?

A - SAP Project System

B - SAP Quality Management

C - SAP Material Management

D - SAP Supply Chain Management

Answer : C

Explanation

SAP Materials Management (MM) is a part of Logistics area and helps to manage the procurement activity of an organization from procurement.

Q 2 - Which of the following material is kept under stock once received from vendor?

A - Procurement for direct consumption

B - Procurement for Stock

C - Procurement for production order

D - None of these

Answer : B

Q 3 - Which of the following element is a commercial organizational unit in R/3 system and is at highest level in SAP system?

A - Company Code

B - Client

C - Plant

D - Storage Location

Answer : B

Q 4 - Which of the following movement type cant be reversed in Warehouse?

A - 101

B - 102

C - 121

D - 122

Answer : C

Answer : E

Explanation

Four basic and must assignments in standard SAP are −

  • Plant to Company code
  • Purchasing organization to company code
  • Purchasing organization to Plant
  • Standard purchasing organization to plant

Q 7 - Scheduling agreement is a long term outline agreement between vendor and ordering party over a predefined material or service which are procured on predetermined dates over a framework of time?

A - True

B - False

Answer : A

Explanation

Scheduling agreement is a long term outline agreement between vendor and ordering party over a predefined material or service which are procured on predetermined dates over a framework of time. Scheduling agreement can be created by following two steps −

  • Creating scheduling agreement
  • Maintain scheduling lines for the agreement

Q 8 - (Quota Allocated Quantity + Quota Base Quantity)/Quota is called?

A - Quota Arrangement

B - Quota Quality

C - Quota Rating

D - None of these

Answer : D

Explanation

Quota rating can be calculated by following formula −

Quota rating = (Quota Allocated Quantity + Quota Base Quantity)/Quota

Where Quota Allocated Quantity is total quantity from all orders that is procured from a particular source. Quota Base Quantity is quantity from new source of supply. Quota is total requirement of material that is given to a particular source of supply.

Q 9 - Stock need to be blocked in advance so that it can be available at a particular point of time. This is known as?

A - RFQ

B - Reservation

C - Plant Manitanance

D - Quota Arrangement

Answer : B

Q 10 - You can make changes to Purchase Order once it is released?

A - True

B - False

Answer : A

Explanation

You can make changes to Purchase Order when it is released. When it is significant change it will retrigger approval cycle.