Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In Production Planning, which of the following is first step to start Production process?

A - Production order confirmation

B - Issuing goods for production order

C - Converting planned order to Production Order

D - Issue the production order

Answer : C

Explanation

Converting planned order to Production Order −

First step is to convert a planned order to production order. When you create a Production Order, type is defined in SAP PP system.

Q 2 - In SAP Production Planning, how many BOMs can be created as per material type?

A - 100

B - 99

C - 50

D - 49

Answer : B

Q 3 - Which of the following T-code can be used to change Routing in PP?

A - CA01

B - CA02

C - CA03

D - CA04

Answer : B

Q 4 - SAP Production Planning is integrated with which of the following modules?

A - Material Management

B - Sales and Distribution

C - Controlling

D - SAP QM

E - All of the above

Answer : E

Q 5 - Which of the following movement type is used to transfer Posting to storage location?

A - 301

B - 302

C - 305

D - 311

Answer : D

Q 6 - Which of the following is performed using Planning table and orders are processed as define in work center to meet the Production process?

A - Capacity Planning

B - Capacity Leveling

C - Capacity Requirement gathering

D - All of these

Answer : B

Explanation

Capacity leveling is performed for performing detailed production planning purpose. This is done through planning table which is used to carry detailed planning of capacity requirements over time in future.

Q 7 - Which of the following is used to generate static report that contains planning run material wise and it displays time of MRP run at the top?

A - MRP List

B - Stock/Requirement List

C - Long Term Planning

D - All of the above

Answer : A

Explanation

MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.

Use T-Code MD05 or go to Logistics → Production → MRP → Evaluation → MRP list

Q 8 - When raw material is consumed to produce material as per Production order, to perform goods issue movement type is?

A - 251

B - 101

C - 261

D - 103

Answer : C

Explanation

In SAP PP, goods issue is done when raw material is consumed to produce material as per Production order. When goods are issued, system decreases the inventory of components at the storage location in Production Planning system.

Movement type 261 is used for goods issue.

Q 9 - A Storage location is defined as location where materials are stored in plant?

A - True

B - False

Answer : A

Q 10 - Long term planning is almost similar to Material requirement planning in simulate version to predict the production plan as per future requirements?

A - True

B - False

Answer : A