SAP PP Online Quiz


Advertisements


Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?

A - Repetitive production

B - Discrete Production

C - Manufacturing Production

D - Material Requirement Planning

Answer : B

Explanation

Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.

In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.

Q 2 - When you specially tailor the make-to-order production of products as per requirements of the customers, which of the following BOM can be used?

A - Material BOM

B - Cost BOM

C - Equipment BOM

D - Sales Order BOM

Answer : D

Explanation

Sales Order BOM is used when you specially tailor the make-to-order production of products as per requirements of the customers. To meet the customer requirements, you make sales order specific modifications to various assemblies.

Answer : E

Q 4 - Which of the following movement type is used for Goods Receipt in to Warehouse?

A - 101

B - 102

B - 103

B - 122

Answer : A

Q 5 - Which of the following doesn’t represent an issue Material Requirement Planning element?

A - Sales Order

B - PIR

C - Transfer Order

D - Production Order

Answer : D

Explanation

Issues include PIRs, Dependent Requirements, Order Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. and receipts include Production Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock Transfer Order, Schedule lines, etc.

Q 6 - In Long Term Planning, to create an inactive version of Planned Independent requirement PIR what is version type?

A - 01

B - 02

C - 03

D - 04

Answer : B

Answer : B

Explanation

NetChange in planning horizon −

This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.

In this run, system consider only those material which has undergone some changes from their last MRP run.

Answer : C

Explanation

Good receipt is performed when material is produced as per Production order and goods is placed at storage location. The stock quantity is increased and movement type 101 is entered.

Q 9 - Material Requirement Planning can be performed at?

A - Single Item –single Level & Plant

B - Routing Level

C - None of the above

D - All of these

Answer : A

Q 10 - To set your PIR version active, which of the below value should be used to specify requirement would be considered in material requirement planning?

A - 00

B - 01

C - 02

D - 03

Answer : A

Explanation

In SAP PP, demand management is performed by Planned Independent requirement PIR. Planned Independent requirement provides input for production planning. A PIR contains one planned quantity of product and one date for material or a planned quantity is split over a span of time period.

To set your PIR version active use value 00 to specify requirement would be considered in material requirement planning. To maintain number of versions of planned independent requirement, you can set some numbers to active and others to inactive.


sap_pp_questions_answers.htm

Advertisements