SAP PP Online Quiz


Advertisements


Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In Material Requirement Planning, which of the following table contains document header data?

A - MDKP

B - MDTB

C - MDVM

D - MDFD

Answer : A

Explanation

MDKP Document Header data

MDTB Table Structure

MDVM Planning File Details

MDFD MRP Date details

Q 2 - When you specially tailor the make-to-order production of products as per requirements of the customers, which of the following BOM can be used?

A - Material BOM

B - Cost BOM

C - Equipment BOM

D - Sales Order BOM

Answer : D

Explanation

Sales Order BOM is used when you specially tailor the make-to-order production of products as per requirements of the customers. To meet the customer requirements, you make sales order specific modifications to various assemblies.

Q 3 - You can use Work center to monitor which of the following activities?

A - Scheduling

B - Production Costing

C - Capacity Planning

D - All of the above

Answer : D

Q 4 - Which of the following movement type is used for Goods Receipt in to Warehouse?

A - 101

B - 102

B - 103

B - 122

Answer : A

Q 5 - Which of the following doesn’t represent an issue Material Requirement Planning element?

A - Sales Order

B - PIR

C - Transfer Order

D - Production Order

Answer : D

Explanation

Issues include PIRs, Dependent Requirements, Order Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. and receipts include Production Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock Transfer Order, Schedule lines, etc.

Q 6 - Which of the following Order type is used to define the material to be produced, plant location where production has to be done, date and time, quantity of goods required?

A - Production Order

B - Planned Order

C - Purchase Order

D - Sales Order

Answer : A

Explanation

A Production order is used to define the material to be produced, plant location where production has to be done, date and time of production, quantity of goods required. A Production Order also defines which components and sequence of operations are to be used and how the order costs are to be settled.

Q 7 - Which of the following is used to generate static report that contains planning run material wise and it displays time of MRP run at the top?

A - MRP List

B - Stock/Requirement List

C - Long Term Planning

D - All of the above

Answer : A

Explanation

MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.

Use T-Code MD05 or go to Logistics → Production → MRP → Evaluation → MRP list

Q 8 - Goods issue can be cancelled till order status is confirmed CNF in system?

A - True

B - False

Answer : A

Q 9 - Which of the following report is used to collect information about hierarchy of work center of a shift?

A - Shift Transfer Report

B - Shift Report

C - Shift Work center Report

D - None of these

Answer : B

Q 10 - Long term planning is almost similar to Material requirement planning in simulate version to predict the production plan as per future requirements?

A - True

B - False

Answer : A


sap_pp_questions_answers.htm

Advertisements