SAP PP - Routing



Routine defines the list of activities to be performed for the production process. Routing defines a sequence of activities performed at the work center. Routing plays in important role in calculating production cost, machine time and labor time.

Key Features Related to Routing

  • To create routing, it is mandatory to first define the work center.

  • Multiple materials can follow through a single routing group.

  • Routing is used for scheduling and costing of operation for raw and finished products.

  • Routing is used to calculate the operation cost for a finished product.

How to Create Routing in PP?

Use T-Code: CA01 or go to Logistics → Production → Master Data → Routings → Routings → Standard Routings → Create

Create Routing

Enter the following details −

  • Material for which routing needs to be defined
  • Plant Code
  • Routing validity date as key date
Routing Initial Screen

Go to the routing header and enter the following details −

  • Usage as 1: Production routing and will be used in Production Order.

  • Select Status as 4 shows the released status. It indicates that routing is valid for material requirement planning and costing.

  • Mention the Lot Size 9999999, which means that routing is valid for order quantity between 0 and 9999999.

  • You can go to Operation button to add the sequence of operation and repeat the above step.

Routing Header Details

Now we need to maintain Operation data for which we need to −

  • Enter the Work Center code.

  • Select Input Control Key to determine the operation to be scheduled, costed, etc.

  • Enter the base quantity and set up time in minutes for base quantity.

  • Enter machine time in minutes for base quantity.

Work Center Code

Click Save and you will get a confirmation that routing is saved.

Routing Saved

How to Change Routing in PP?

Use T-Code: CA02 or go to Logistics → Production → Master Data → Routings → Routings → Standard Routings → Change

SAP PP Routing

Enter the following details −

  • Material for which routing needs to be defined.

  • Plant Code.

  • Routing validity date as the key date.

Routing Validity

You can change the values like Control key or machine time.

Control Key

Click Save to make the changes.