- PMP ® Exams Tutorial
- PMP - Exams - Home
- PMP - Exams Overview
- PMP ® Sample Questions
- PM - Fundamentals
- Integration Management
- Project Scope Management
- Project Time Management
- Project Cost Management
- Project Quality Management
- Human Resource Management
- Communication Management
- Project Risk Management
- Procurement Management
- Stakeholder Management
- PMP ® Mock Exams
- PMP® - Mock Exams
- PMP® - Sample Questions
- PMP ® Exams Resources
- PMP® - Quick Guide
- PMP® - Exams Resources
- PMBOK® Guide 5th Edition
- PMBOK® Guide 4th Edition
- PMP® Exams - Discussion
PMP Sample Questions
Based on PMBOK 5th Edition
Here are 200 more objective type sample questions and their answers are given just below to them. This exam is just to give you an idea of type of questions which may be asked in PMP Certification Exams. Even we have taken full care to give correct answers for all the questions but it is recommended to verify these answers.
In examination you will get each question one by one on computer screen
101 A particular stakeholder has a reputation for making many changes on projects. What is the best approach a project manager can take at the beginning of the project to manage this situation?
Answer : B
Hint: Early involvement of active and contributing stakeholders is always good.
102 The WBS component used for the project cost accounting is called:
Answer : C
Hint: PMBOK 5, Page199, 'Organizational Procedures Links'
103 A major negotiation with a potential subcontractor is scheduled for tomorrow when you discover there is a good chance the project will be cancelled. What should you do?
Answer : D
Hint: It is advisable to put new things on hold in such cases.
104 A project manager is preparing the budget for the project. There are several inputs to the budgeting process that the project manager will use. One of the things that the project manager will not use is the:
Answer : C
Hint: Cost baseline includes the budget.
105 The project status report is an example of which form of communication?
Answer : A
Hint: A project status report is a formal document for a record.
106 What are the major advantages of the functional type of organization?
Answer : B
Hint: In a functional organization, every resource is owned by a department and hierarchy.
107 A project on software development and construction of a bridge are similar to each other in terms of:
Answer : B
Hint: These projects differ in all aspects except for the process groups
108 In matrix management organizations, if the organization maintains many of the characteristics of the functional organization and the project managers are considered more like project coordinators or expediters, it is called a:
Answer : C
Hint: Among matrix organizations, weak matrix is closed to a functional organization.
109 All of the following are part of the scope baseline EXCEPT the:
Answer : A
Hint: PMBOK 5, Page 131, Sec 5.4.3.1 Scope Baseline
110 You are asked to select tools and techniques to implement a quality assurance program to supplement existing quality control activities. Which of the following would you choose?
Answer : A
Hint: PMBOK 5, Page 245, Sec 8.2.2 Perform Quality Assurance: Tools and Techniques
111 The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?
Answer : C
Hint: PMBOK 5, Page 193, 7.3 Determine Budget
112 During what part of the project management process is the project scope statement created?
Answer : B
Hint: Scope statement is done as a part of planning
113 One of the most important duties that the project manager can perform is the function of:
Answer : D
Hint: A project manager mainly focuses on integration of work under all knowledge areas.
114 With a clear contract statement of work, a seller completes work as specified, but the buyer is not pleased with the results. The contract is considered to be:
Answer : C
Hint: The work is done as specified so it meets the acceptance criteria. Hence it is complete.
115 The organization that is a formalized structure directed toward the support of the project community within the organization is called
Answer : D
Hint: PMBOK 5, Page 11, Sec 1.4.4 Project Management Office
116 You have always been asked by your management to cut your project estimate by ten percent after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation?
Answer : C
Hint: The best approach would be to provide accurate figures and support the estimate with historical information in past projects documents.
117 Which of the following is the best project management tool to use to determine the longest time the project will take?
Answer : B
Hint: PMBOK 5, Page 159, Sec 6.3.3.1. Project Schedule Network Diagrams
118 In a large organization a project expediter is being used to manage a project for an important client. The position of project expediter would be found in what kind of an organization?
Answer : B
Hint: PMBOK 5, Page 23, 1st paragraph
119 Herzberg divided motivation factors into two classes: satisfiers and dissatisfiers. Examples of satisfiers are:
Answer : D
Hint: Compare hygiene factors with motivators to know the difference. Recognition and achievement are satisfiers.
120 One of the important techniques used in the development of a Project Charter is the Expert Judgement that is available from the following source excluding?
Answer : D
Hint: Project Manager is not responsible for developing project charter
121 Two people are arguing about what needs to be done to complete a work package. if the project manager wants to know what is going on, she should pay MOST attention to:
Answer : D
Hint: To understand the situation completely, all the factors (Who, What, How) are important
122 The skill of listening involves more than just hearing the sounds. One of the characteristics of a good listener is that he or she:
Answer : C
Hint: Repeating what we listen reinforces the knowledge and give feedback to the speaker
123 A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the best explanation for why this occurred?
Answer : D
Hint: SPI<1 means less work was completed than what was planned, CPI <1 indicates a cost overrun.
124 A new software installation project is in progress. The project manager is working with the quality assurance department to improve everyone's confidence that the project will satisfy the quality standards. Which of the following MUST they have before they start this process?
Answer : C
Hint: It is important to know the performance indicators or control limits before any test.
125The project is not completed until:
Answer : B
Hint: Meeting the acceptance criteria and receiving a formal acceptance is mandatory for completion
126 Primary outputs from Develop Project Team are:
Answer : A
Hint: PMBOK 5, Page 278, Sec 9.3.3 Develop Project Team: Outputs
127 All of the following are the responsibility of a project manager EXCEPT?
Answer : B
Hint: A project manager must focus on projects and not on company rules and regulations
128 Enterprise Environmental Factors that influence the development of a Project Management Plan include:
Answer : D
Hint: PMBOK 5, Page 29, Sec. 2.1.5 Enterprise Environmental Factors
129 A project manager for the seller is told by her management that the project should do whatever possible to be awarded incentive money. The primary objective of incentive clauses in a contract is to:
Answer : C
Hint: PMBOK 5, Page 364, Cost Plus Incentive Fee Contracts
130 A project manager is managing a project where there will be a number of persons working together. She wants to enhance the ability of the team to work together and perform as a team. One of the things that she can do to maximize the ability of the team to do this is:
Answer : B
Hint: Colocation offers many advantages that help enhance team performance
131 A project manager is asked to manage a large complicated project that is located in a remote part of Africa. The project will last for five years and will have the product of producing a nuclear reactor that will generate 900 megawatts of power at start-up. The best kind of organization for managing this project is:
Answer : C
Hint: PMBOK 5, Page 21, Sec 2.1.3 Organizational Structures
131 During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
Answer : A
Hint: PMBOK 5, Page 132, WBS dictionary
132 According to McGregor.s concept of theory X and theory Y, which of the following statements is true?
Answer : B
Hint: Theory Y puts more trust on workers and favors delegation, responsibility, autonomy
133 The summation of the control accounts make up the_________ ?
Answer : B
Hint: PMBOK 5, Page 213, 1st Para.
134 You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves five different sellers and 20 members of your company on the project team. You want to quickly review where the project now stands. Which of the following reports would be the most helpful in finding such information?
Answer : B
Hint: Progress reports will help in tracking the completed work versus the planned work
135 The customer on a project tells the project manager he has run out of money to pay for the project. What should the project manager do first?
Answer : B
Hint: If the funds aren't available, the project must be formally closed.
136 The Organizational Process Assets that influence the Monitor and Control Project Work Process include all but?
Answer : c
Hint: PMBOK 5, Page 27, Sec. 2.1.4 Organizational Process Assets
137 Omar, a project manager in a construction company is preparing for a meeting with the stakeholders to update them about the status of the project after the monitoring and controlling of the project work. For the information, Omar will access automated tools such as performance indicators, databases, financials, or resourcing tools through:
Answer : A
Hint: PMBOK 5, Page 29, Sec. 2.1.5 Enterprise Environmental Factors
138 A project manager has been overwhelmed with problems on his project. He would like to identify the root cause of the problems in order to determine where to focus his attention. Which of the following tools would be BEST for the project manager to use?
Answer : C
Hint: Fishbone or Ishikawa diagrams are tools used for cause and effect analysis
139 The client changes the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do?
Answer : C
Hint: The project sponsor is the most important stakeholder in the performing organization
140 Lag means:
Answer : C
Hint: Any delay in time between two successive activities is known as lag.
141 A routine audit of a cost reimbursable (CR) contract determines that overcharges are being made. If the contract does not specify corrective action, the buyer should:
Answer : A
Hint: If the contract doesn't include a condition, then the payment must be made.
142 A project manager is in the middle of the executing process of a verylarge construction project when he discovers that the time needed to complete the project is longer than the time available. What is the BEST thing to do?
Answer : D
Hint: Schedule compression techniques are used when a project gets behind the schedule.
143 You are a new project manager who has never managed a project before. You have been asked to plan for a new project. It would be BEST in this situation to rely on which of the following during planning in order to improve your chance of success..
Answer : C
Hint: Historical information contained in organizational process assets must be utilized
144 During which phase of a project life cycle, will risk be the lowest??
Answer : D
Hint: Risk and uncertainty are highest in the beginning and diminish towards the project completion. PMBOK 5, Page 40, Figure 2-9
145 A project manager is managing a project where a risk occurs. There is no plan to respond to this risk. The response to a negative risk event that has no planned response is called:
Answer : B
Hint: Workarounds are risk responses not initially planned.
146 A project manager is dealing with risk analysis on a software development project. There is a risk that the module that creates the most important report will not work properly. It will require another 200 person-hours to fix the bugs. The project manager decides to do nothing about this risk. Which of the following risk strategies is the project manager employing?
Answer : A
Hint: Risk Acceptance means not creating any mitigation plans.
147 A trucking company expects to purchase 525 truck tires over the next year for their fleet. The company places a blanket order for the tires to a local tire vendor. At the end of year, the company has only purchased 500 of the tires. What should be done to close the contract??
Answer : A
Hint: Terms of contract must be fulfilled
148 You are the project manager for a large project under contract with the government. The contract for this two year, multi-million dollar project was signed six months ago. You were not involved in contract negotiations or setting up procedures for managing changes, but now you are swamped with changes from the customer and from people inside your organization. Who is normally responsible for formally reviewing major changes to the project contract??
Answer : A
Hint: Change control board is a formal group that is responsible for reviewing, approving or rejecting project changes. It also records and communicates the decision taken for any change request.
149 In Manage Communications process, the techniques and considerations for effective communications management include all but?
Answer : D
Hint: PMBOK 5, Page 298
150 A project manager managing any project should perform risk analysis at what stage of the project:
Answer : B
Hint: Risk Identification and Management is an ongoing activity