EVM - Examples


Advertisements

To illustrate the concept of EVM and all the formulas, assume a project that has exactly one task. The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The task would have been completed already.

Assume an Hourly Rate of $100 per hour.

Using this information -

PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled

PV = $100 × 8 hours = $800

AC or ACWP = Hourly Rate × Total Hours Spent

AC = $100 × 11 hours = $1100

EV or BCWP = Baselined Cost × % Complete Actual

EV = baseline of $800 × 91.7% complete = $734

(NOTE % Complete Actual (below) to get the 91.7%)

BAC = Baselined Effort − hours × Hourly Rate

BAC = 8 hours × $100 = $800

EAC = AC + ETC

EAC = 1100 + 100 = $1200

VAC = BAC − EAC

VAC = $800 − $1200 = −$400

% Completed Planned = PV ⁄ BAC

% Complete Planned = $800 PV ⁄ $800 BAC = 100%

% Completed Actual = AC ⁄ EAC

% Complete Actual = $1100 AC ⁄ $1200 EAC = 91.7%

SV = Earned Value (EV) − Planned Value (PV)

SV = $734 EV − $800 PV = −$66

SPI = Earned Value (EV) ⁄ Planned Value (PV)

SPI = $734 EV ⁄ $800 PV = 0.91

CV = Earned Value (EV) − Actual Cost (AC)

CV = ($734 EV − $1100 AC) = −$366*

* indicates a cost overrun

CPI = Earned Value (EV) ⁄ Actual Cost (AC)

CPI = $734 EV ⁄ $1100 AC = 0.66*

* indicates over-budget

Useful Video Courses


Video

Learn Python Programming in 100 Easy Steps

136 Lectures 11 hours

In28Minutes Official

Video

Learn Java Programming for Beginners in 250 Easy Steps

288 Lectures 25 hours

In28Minutes Official

Video

Learn C++ Pointers with Visual Studio 2017

14 Lectures 57 mins

Kaushik Roy Chowdhury

Video

Mathematics for Data Science and Machine Learning using R

Most Popular

64 Lectures 10.5 hours

Eduonix Learning Solutions

Video

React and Redux: Learn By Building Real World Projects

56 Lectures 12.5 hours

Eduonix Learning Solutions

Video

Java Essentials : Learn Core Java From Basic to Advance

53 Lectures 9 hours

Anshul Chauhan

Advertisements