SAP PP Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?

A - Repetitive production

B - Discrete Production

C - Manufacturing Production

D - Material Requirement Planning

Answer : B

Explanation

Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.

In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.

Q 2 - When you specially tailor the make-to-order production of products as per requirements of the customers, which of the following BOM can be used?

A - Material BOM

B - Cost BOM

C - Equipment BOM

D - Sales Order BOM

Answer : D

Explanation

Sales Order BOM is used when you specially tailor the make-to-order production of products as per requirements of the customers. To meet the customer requirements, you make sales order specific modifications to various assemblies.

Answer : A

Explanation

Key Features related to Routing −

To create routing it is mandate that you first define work center.

Multiple material can follow single routing group.

Routing is used for scheduling and costing of operation for raw and finished products.

Routing is used for calculation operation cost for finished product.

Q 4 - Which of the following Planning strategy is used to produce stock without Sales Order?

A - Make to Order

B - Make to Stock

C - Both of These

D - None of these

Answer : B

Q 5 - After MRP run, which of the following gets created in Planning?

A - Production Order & Planned Order

B - Purchase Order

C - None of the above

D - Scheduling Lines

Answer : A

Q 6 - Which of the following is performed using Planning table and orders are processed as define in work center to meet the Production process?

A - Capacity Planning

B - Capacity Leveling

C - Capacity Requirement gathering

D - All of these

Answer : B

Explanation

Capacity leveling is performed for performing detailed production planning purpose. This is done through planning table which is used to carry detailed planning of capacity requirements over time in future.

Q 7 - Which of the following is used to generate static report that contains planning run material wise and it displays time of MRP run at the top?

A - MRP List

B - Stock/Requirement List

C - Long Term Planning

D - All of the above

Answer : A

Explanation

MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.

Use T-Code MD05 or go to Logistics → Production → MRP → Evaluation → MRP list

Q 8 - To check the available stock at any point of time, which of the following can be used?

A - Capacity Leveling

B - Stock overview

C - Stock/Requirement List

D - All of these

Answer : B

Explanation

You can use Stock overview to check the available stock at any point of time. Stock overview can be checked using T-Code: MMBE or go to Logistics → Materials Management → Inventory Management → Environment → Stock → Stock Overview

Q 10 - Which of the following Transaction can be used confirm a Production Order and for Goods movement?

A - CO01

B - CO02

C - CO15

D - MD16

Answer : C

Explanation

To confirm Production Order, use T-code: CO15

You can perform following activities −

  • Generate confirmation document
  • Consume raw materials or semi-finished goods
  • Good receipt of finished goods or semi-finished goods
sap_pp_questions_answers.htm
Advertisements