SAP PP Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In Material Requirement Planning, which of the following table contains document header data?

A - MDKP

B - MDTB

C - MDVM

D - MDFD

Answer : A

Explanation

MDKP Document Header data

MDTB Table Structure

MDVM Planning File Details

MDFD MRP Date details

Q 2 - In SAP Production Planning, how many BOM’s can be created as per material type?

A - 100

B - 99

C - 50

D - 49

Answer : B

Answer : E

Answer : A

Explanation

When you use Planning strategy 10, only PIR quantity is considered for MRP run and sales order are completely ignored. In this PIR requirement type LSF and is reduced when you deliver stock to customer.

Q 5 - Which of the following doesn’t represent an issue Material Requirement Planning element?

A - Sales Order

B - PIR

C - Transfer Order

D - Production Order

Answer : D

Explanation

Issues include PIRs, Dependent Requirements, Order Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. and receipts include Production Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock Transfer Order, Schedule lines, etc.

Q 6 - Which of the following Order type is used to define the material to be produced, plant location where production has to be done, date and time, quantity of goods required?

A - Production Order

B - Planned Order

C - Purchase Order

D - Sales Order

Answer : A

Explanation

A Production order is used to define the material to be produced, plant location where production has to be done, date and time of production, quantity of goods required. A Production Order also defines which components and sequence of operations are to be used and how the order costs are to be settled.

Answer : B

Explanation

NetChange in planning horizon −

This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.

In this run, system consider only those material which has undergone some changes from their last MRP run.

Answer : C

Explanation

Good receipt is performed when material is produced as per Production order and goods is placed at storage location. The stock quantity is increased and movement type 101 is entered.

Q 9 - Material Requirement Planning can be performed at?

A - Single Item –single Level & Plant

B - Routing Level

C - None of the above

D - All of these

Answer : A

Answer : C

sap_pp_questions_answers.htm
Advertisements