SAP PP Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?

A - Repetitive production

B - Discrete Production

C - Manufacturing Production

D - Material Requirement Planning

Answer : B

Explanation

Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.

In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.

Q 2 - When you create a Material BOM without a Plant is known as?

A - Reference BOM

B - Master BOM

C - Group BOM

D - Master group

Answer : C

Q 3 - To create routing it is mandate that you first define work center?

A - True

B - False

Answer : A

Q 4 - For Make to Order process, which of the following Planning strategy is used?

A - 20

B - 25

C - 30

D - 35

Answer : A

Explanation

You use Planning strategy 20 for make to order MTO process and planning strategy 25 is used to produce product variants when there is request for variant products from customer

Q 5 - After MRP run, which of the following gets created in Planning?

A - Production Order & Planned Order

B - Purchase Order

C - None of the above

D - Scheduling Lines

Answer : A

Q 6 - In Long Term Planning, to create an inactive version of Planned Independent requirement PIR what is version type?

A - 01

B - 02

C - 03

D - 04

Answer : B

Q 7 - In which of MRP type, system consider all the material irrespective of changes and it is time consuming and not common in Production planning?

A - NetChange

B - NetChange in Planning horizon

C - Regenerative Planning

D - None of these

Answer : C

Explanation

NetChange

In this run system consider those material which has undergone some changes from the previous MRP run.

NetChange in planning horizon

This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.

In this run, system consider only those material which has undergone some changes from their last MRP run.

Regenerative Planning

In this run, system consider all the material irrespective of changes and it is time consuming and not common in Production planning.

Answer : C

Explanation

Good receipt is performed when material is produced as per Production order and goods is placed at storage location. The stock quantity is increased and movement type 101 is entered.

Answer : A

Q 10 - Which of the following Transaction can be used confirm a Production Order and for Goods movement?

A - CO01

B - CO02

C - CO15

D - MD16

Answer : C

Explanation

To confirm Production Order, use T-code: CO15

You can perform following activities −

  • Generate confirmation document
  • Consume raw materials or semi-finished goods
  • Good receipt of finished goods or semi-finished goods
sap_pp_questions_answers.htm