- SAP PM Tutorial
- SAP PM - Home
- SAP PM - Overview
- SAP PM - Technical Objects
- SAP PM - Equipment Master Record
- Functions of Technical Objects
- SAP PM - Creating Multilingual Text
- SAP PM - Breakdown Maintenance
- SAP PM - Corrective Maintenance
- SAP PM - Creating/Planning MO
- SAP PM - Preventive Maintenance
- SAP PM - Maintenance Planning
- Project Oriented Maintenance
- SAP PM - Refurbishment Process
- SAP PM - Warranty Claim Processing
- Mobile Applications For EAM
- Work Clearance Management
- SAP PM - Information System
- Cross Application Time Sheet
- SAP PM - Single & Composite Roles
- SAP PM Useful Resources
- SAP PM - Questions Answers
- SAP PM - Quick Guide
- SAP PM - Useful Resources
- SAP PM - Discussion
- Selected Reading
- UPSC IAS Exams Notes
- Developer's Best Practices
- Questions and Answers
- Effective Resume Writing
- HR Interview Questions
- Computer Glossary
- Who is Who
SAP PM Mock Test
This section presents you various set of Mock Tests related to SAP PM. You can download these sample mock tests at your local machine and solve offline at your convenience. Every mock test is supplied with a mock test key to let you verify the final score and grade yourself.

SAP PM Mock Test IV
Q 1 - Which of the following functions can be performed on mobile devices w.r.t Enterprise Asset Management?
Answer : G
Explanation
You can perform following functions on mobile devices w.r.t Enterprise Asset Management −
- Order Processing
- Notification Processing
- Enter Measurement Readings
- Stock Processing
- Management of Technical Objects
Q 2 - Which of the following is correct?
Maintenance Plan Type Maintenance Strategy
1) Single cycle plan, time-based No
2) Single cycle plan, performance-based No
3) Strategy plan, time-based Yes
4) Strategy plan, performance-based Yes
5) Multiple counter plan No
Answer : E
Q 3 - Which of the time based scheduling allows you to perform Maintenance strategy every 30 working days?
Answer : C
Explanation
Time-based (for example, every 30 days)
Time-based by key date (for example, every 30 days on the 30th day of the month)
Time-based by factory calendar (for example, every 30 working days)
Q 4 - When you create a maintenance strategy plan for a Printer to be performed after 1 million copies, it is example of?
Answer : B
Q 5 - When you assign multiple packages with different cycle duration to a strategy, all packages can have different dimensions?
Answer : B
Q 6 - Which of the following is used to define which preventive maintenance tasks should take place regularly at a technical object or a group of technical objects?
Answer : C
Explanation
A maintenance item describes which preventive maintenance tasks should take place regularly at a technical object or a group of technical objects.
Answer : A
Q 9 - Which of the following are the technical objects?
Answer : B
Q 10 - A Repair is known as- all measures which restore the ideal condition of a technical system?
Answer : A
Q 11 - Which of the following correctly defines a Maintenance Plant?
B - Plant at which maintenance activities are planned
C - Plant at which Maintenance of material done
D - A plant in which the technical objects of a company are installed
Answer : D
Explanation
Q 12 - In Plant Maintenance, you can make a location field as mandatory in IW31 T-Code?
Answer : A
Explanation
Yes, in T-code: IW31 → Location → Location Tab (Mandatory)
Plant Maintenance and Customer Service → Maintenance and Service Processing → Maintenance and Service Orders → Define Field Selection for Order Header Data
(PM)--- Field Selection for Location/Account Assignment Data
Q 13 - In SAP Plant Maintenance, which of the following role is responsible to perform planning maintenance tasks based on incoming malfunction reports and is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery?
Answer : B
Explanation
In SAP Plant Maintenance, a Maintenance planner is responsible for planning maintenance tasks based on incoming malfunction reports. Maintenance planner is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery.
Answer Sheet
Question Number | Answer Key |
---|---|
1 | G |
2 | E |
3 | C |
4 | B |
5 | B |
6 | C |
7 | A |
8 | D |
9 | B |
10 | A |
11 | D |
12 | A |
13 | B |