Parallel Courses III - Problem
Parallel Courses III is an advanced scheduling problem where you need to find the minimum time to complete all university courses given prerequisite constraints.
You have
• A specific duration (in months) to complete
• Zero or more prerequisite courses that must be finished first
Key Rules:
• You can start any course immediately if all its prerequisites are met
• Multiple courses can be taken simultaneously (parallel processing)
• The goal is to minimize total completion time
Input: Number of courses
Output: Minimum months needed to complete all courses
Think of this as optimizing a project timeline where some tasks depend on others, but independent tasks can run in parallel.
You have
n courses labeled from 1 to n, where each course has:• A specific duration (in months) to complete
• Zero or more prerequisite courses that must be finished first
Key Rules:
• You can start any course immediately if all its prerequisites are met
• Multiple courses can be taken simultaneously (parallel processing)
• The goal is to minimize total completion time
Input: Number of courses
n, prerequisite relationships relations[][], and course durations time[]Output: Minimum months needed to complete all courses
Think of this as optimizing a project timeline where some tasks depend on others, but independent tasks can run in parallel.
Input & Output
example_1.py — Linear Chain
$
Input:
n = 3, relations = [[1,3],[2,3]], time = [3,2,5]
›
Output:
8
💡 Note:
Courses 1 and 2 can start simultaneously and finish at months 3 and 2 respectively. Course 3 can start at month 3 (when both prerequisites are done) and finishes at month 3+5=8.
example_2.py — Single Course
$
Input:
n = 1, relations = [], time = [1]
›
Output:
1
💡 Note:
Only one course with no prerequisites, takes 1 month to complete.
example_3.py — Complex Dependencies
$
Input:
n = 5, relations = [[1,5],[2,5],[3,5],[3,4],[4,5]], time = [1,2,3,4,5]
›
Output:
12
💡 Note:
Course 3 finishes at month 3, course 4 at month 7 (3+4), and course 5 at month 12 (7+5). Courses 1 and 2 finish earlier but don't affect the critical path.
Constraints
- 1 ≤ n ≤ 5 × 104
- 0 ≤ relations.length ≤ min(5000, n × (n - 1) / 2)
- relations[j].length == 2
- 1 ≤ prevCoursej, nextCoursej ≤ n
- prevCoursej ≠ nextCoursej
- All the pairs [prevCoursej, nextCoursej] are unique
- time.length == n
- 1 ≤ time[i] ≤ 104
- The given graph is a directed acyclic graph (DAG)
Visualization
Tap to expand
Understanding the Visualization
1
Map Dependencies
Build a graph where edges represent prerequisite relationships
2
Find Starting Courses
Identify courses with no prerequisites - these can start immediately
3
Process in Order
Use topological sorting to process courses in dependency order
4
Calculate Times
For each course, its earliest start time is when all prerequisites are done
Key Takeaway
🎯 Key Insight: The minimum time is determined by the longest dependency chain (critical path), not the sum of all course times. Parallel execution of independent courses is automatically optimized through topological sorting.
💡
Explanation
AI Ready
💡 Suggestion
Tab
to accept
Esc
to dismiss
// Output will appear here after running code