Anil Sunil and Rajat can complete a work in 4 hours. If Anil does the work in 12 hour, Sunil in 10 hours . How long it take to Rajat to finish the alone
Given:
Anil, Sunil, and Rajat can complete a work in 4 hours.
Anil does the work in 12 hours and Sunil in 10 hours.
To find:
Here, we have to find how long will Rajat take to finish the work.
Solution:
We would consider total work to be 1.
Work done by Anil in one hour = $\frac{Total\ work}{Total\ number\ of\ hours\ taken}$
Work done by Anil in one hour $= \frac{1}{12}$.
Similarly,
Work done by Sunil in 1 hour$=\frac{1}{10}$
Work done by Rajat in one hour be $\frac{1}{x}$.
Therefore,
Total work done by all three in one hour $= \frac{1}{12}\ +\ \frac{1}{10}\ +\ \frac{1}{x}$
Work done in one hour $\times$ Total number of hours $=$ Total work
$[\frac{1}{12}\ +\ \frac{1}{10}\ +\ \frac{1}{x}]\ \times\ 4\ =\ 1$
$\frac{1}{12}\ +\ \frac{1}{10}\ +\ \frac{1}{x}\ =\ \frac{1}{4}$
$\frac{1}{x}\ =\ \frac{1}{4}\ -\ \frac{1}{12}\ -\ \frac{1}{10}$
$\frac{1}{x} \ =\ \frac{1\times15\ -\ 1\times5\ -\ 1\times6}{60}$
$\frac{1}{x} \ =\ \frac{4}{60}$
$x=\frac{60}{4}$
$x=15$
$x = 15\ hours$
So, Rajat can complete the same work in 15 hours.
Related Articles
- A, B and C together finish a work in 4 days if A alone can finish the same work in 8 days and B in 12 days. Find how long will C take to finish the work?
- A and B together can do a piece of work in 10 days if an alone will take 12 days to finish the work how long will B take to do the work?
- John does $\frac{1}{2}$ piece of work in 3 hours, Joe does $\frac{1}{4}$ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How long would it have taken the three working together to do the work?
- How to Convert Hours to 8-Hour Work Days in Excel?
- A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
- A car travels 200 km in 4 hours. How long will it take to travel 500 km?
- If two pipes function simultaneously, a reservoir will be filled in 12 hours. One pipe fills the reservoir 10 hours faster than the other. How many hours will the second pipe take to fill the reservoir?
- 2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?
- Formulate the following problems as a pair of equations, and hence find their solutions:(i) Ritu can row downstream 20 km in 2 hours, and upstream 4 km in 2 hours. Find her speed of rowing in still water and the speed of the current.(ii) 2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.(iii) Roohi travels 300 km to her home partly by train and partly by bus. She takes 4 hours if she travels 60 km by train and the remaining by bus. If she travels 100 km by train and the remaining by bus, she takes 10 minutes longer. Find the speed of the train and the bus separately
- What portion of a saree can Zenab paint in $1$ hour if it requires $7$ hours to paint the whole saree?
- A bus can cover 62.5 km in one hour. How much distance can it cover in 18 hours?
- 2 women and 5 men can together finish a piece of embroidery in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the embroidery and that taken by 1 man alone.
- Do meetings during work hours hamper productivity?
- The class teacher gave 150 tickets to Sunil of which he sold 60 percent. How many tickets did Sunil sold?
- A painter works for 4 hours every day from Monday to Friday. What fraction of a week does he work?
Kickstart Your Career
Get certified by completing the course
Get Started