SAP PM Mock Test III

Q 1 - In SAP PM, a new notification can be created with reference from?

A - Order

B - Technical object

C - Functional Location

D - All of these

E - a & b

Answer : D

Q 2 - Which of the following feature helps field service technicians to access all the work related information on their mobile devices?

A - Mobile Applications for EAM

B - Work Clearance Management

C - Cross Application Timesheet

D - Maintenance Event Builder

Answer : A

Q 3 - In Plant Maintenance, after refurbishment is done and material is returned, which of the following is correct?

A - Stock value of the repairable material in the warehouse is changed

B - Charges to the cost center changes

C - A credit memo is applied to the order

D - A & B

E - All of the above

Answer : E

Q 4 - To better manage and monitor Plant Maintenance process in Financial Management, you can integrate Plant Maintenance (PM) and Funds Management (FM)?

A - True

B - False

Answer : A

Q 5 - In Refurbishment process, to move the material to Warehouse which of the following movement type is created?

A - Movement type 101

B - Movement type 102

C - Movement type 103

D - Movement type 104

Answer : A

Q 6 - Arrange the below steps in correct sequence as part of Refurbishment process?

  • Uninstall the damaged Equipment from the Maintenance Plant.

  • Movement type 101, to move the material to Warehouse.

  • Creation of Refurbishment order to collect cost for the refurbishment activity.

  • When Refurbishment process is executed, state of material is changed from damaged to Refurbished.

  • Reinstallation of equipment in the Maintenance plant.

A - 1,2,4,3,5

B - 1,3,2,4,5

C - 1,4,3,2,5

D - 1,2,3,4,5

Answer : D

Q 7 - Which of the following location is used to define maintenance task lists and material planning is carried out?

A - Maintenance Plant

B - Maintenance Planning Plant

C - Warehouse

D -All of the above

Answer : B

Q 9 - Which of the following module is integrated with Plant Maintenance to perform Order settlement to a project or WBS element?

A - Controlling

B - Project System

C - Material Management

D - Production Planning

Answer : B

Q 10 - In SAP Plant Maintenance, Maintenance strategies are mandatory to define maintenance plans?

A - True

B - False

Answer : B

Explanation

Maintenance strategies are optional in Maintenance plans like multiple counter plan.

Q 11 - Which of the following T-code is used to create a Refurbishment order in Plant Maintenance?

A - IW34

B - IW36

C - IW81

D - IW21

Answer : C

Q 12 - Which of the following T-code is used to create a Warranty object?

A - IE01

B - IL01

C - IQ01

D - IB51

Answer : A

Q 13 - Which of the following shows an invalid warranty and negative checks are shown for Warranty claim results?

A - 00

B - 03

C - 01

D - 02

Answer : B

Explanation

  • 00 shows a valid warranty and positive check result are shown.
  • 03 shows an invalid warranty and negative check result are shown.
  • 01 shows no warranty check possible since required measuring point is missing in the warranty claim.
  • 02 shows no warranty check possible since required measurement document is missing in the system.

Answer Sheet

Question Number Answer Key
1 D
2 A
3 E
4 A
5 A
6 D
7 B
8 C
9 B
10 B
11 C
12 A
13 B